Conform to aci 301.
Rubbed concrete wall finishes.
Apply sandblasted finish to exposed concrete surfaces where indicated.
Rubbed finishes smooth rubbed no later than the day following formwork removal wet surface and rub it with an abrasive such as a carborundum brick until a uniform color and texture are produced.
Immediately after removing the forms form ties shall be broken back a minimum of three quarters inch from the surface honeycomb voids and other surface defects grouted.
Wet rubbing is accomplished on green concrete by a slow speed grinding wheel or disc at the same time applying water.
When finish is not indicated provide smooth form finish as specified above.
A popular easy to apply and long lasting finish is called rubbing when you rub out a new concrete wall you are applying a thin coat of portland cement and literally rubbing it with a sponge float to create an attractive and durable finish.
Conform to aci 301.
Cleveland concrete contractor ron simonetti says a smooth rubbed finish done with an abrasive stone should look the same as a grout cleaned sacked finish.
Blasting operations and requirements.
The water plus the rubbing action brings up a cement paste which results in a very smooth plaster like surface.
The surfaces shall then be thoroughly dampened and rubbed with a no.